Q&A includes comments about Bee Cave Road improvements

From Statesman’s Ben Wear: Getting There on 7/9/07:

Q: They widened Bee Cave Road from MoPac up to Eanes Creek about three years ago, and I heard they were to continue west with that. Then nothing happened. What’s up with that?

A: Nothing, unfortunately. The cities of West Lake Hills and Rollingwood were supposed to get right of way for further widening, Daigh said, but were depending on donated land and never got all that was necessary.

Now, with sharply increased construction costs and diversion of some money to other Transportation Department projects, the agency has on hand less than a third of the $34 million construction cost, even if the right of way becomes available.

|